Since Monday, Nov. 2, you can't turn off FM 93 onto Hartrick Bluff Road. The City of Temple has closed the stretch between FM 93 and Wyndham Hill Parkway to through traffic for about 10 months, and it expects this first phase to finish by fall 2027. The closure is the first phase of a project that will make Hartrick Bluff a different class of street. Once the full rebuild is done, the plans call for a three-lane collector with a sidewalk, new drainage, a bridge over Fryer's Creek and a traffic signal at FM 93.
The closure is only the first piece of a longer rebuild, and how it is set up says a lot about what comes after it.
How the Closure Works on an Ordinary Weekday
The city's closure notice lays out the rules for this phase:
- Through traffic is detoured onto Wyndham Hill Parkway and South 5th Street.
- Residents along the closed section get in from the north end. Enter Hartrick Bluff from Wyndham Hill Parkway and drive south. You can't get in from FM 93.
- Services keep running. Mail, school buses, solid waste collection and other deliveries keep their access. The city's project page adds that garbage, recycling and scheduled Brush & Bulky Item pickups continue, and that the city has worked with local school districts to keep bus access open.
- Driveway and cul-de-sac closures come with a week's notice. If work has to close a private driveway or cul-de-sac for a while, affected residents will hear at least one week ahead, and access returns as soon as that section is finished.
For questions, the City of Temple Engineering Department is at 254.298.5660. The project page also lists Glenn Schneider of RT Schneider Construction Co. at 254-534-2394, and Anthony Luke of Walker Partners, the engineering consultant, at 254-910-6750.
The First Work Goes Underground
The city says it is closing the road so crews can install underground utilities and make roadway improvements. That explains the full closure. A road can stay open while crews repave a lane. It's much harder to keep traffic moving while they dig trenches under it.
One of those utilities is water. According to the Temple Daily Telegram, the plans replace the existing 8-inch waterline with a 12-inch line. A 12-inch pipe has more than twice the cross-section of an 8-inch one. That is the kind of upgrade a city makes when a road is expected to serve far more homes than it was built for.
The Road That Comes Back
The full project runs along Hartrick Bluff from FM 93 to Waters Dairy Road. A filing with the Texas Department of Licensing and Regulation, project TABS2026016805, puts it at about 200,000 square feet of new streets, sidewalks, curb ramps and crosswalks. Temple's draft mobility master plan calls it a conversion of a rural road into a collector serving residential subdivisions.
Here is how the full corridor changes under the plans the Telegram described:
| Feature | Planned for FM 93 to Waters Dairy Road |
|---|---|
| Road type | Rural road converted to a collector street |
| Lanes | Widened to a three-lane section |
| Walking | 8-foot sidewalk |
| Fryer's Creek | New bridge |
| Drainage | New drainage infrastructure |
| Water service | Existing 8-inch waterline replaced with a 12-inch line |
| FM 93 intersection | Four-way signal with new left-turn lanes on FM 93 |
The current closure covers only the northern part of that corridor, from FM 93 down to Wyndham Hill Parkway. The table describes the finished project, not what will be done this time next year. The city has said it will share more as construction moves into future phases.
FM 93 Is Getting a Signal
For many drivers, the change they'll notice most every day is at the north end. The project adds new left-turn lanes on FM 93 and a traffic signal where Hartrick Bluff meets it, making it a four-way signalized intersection.
FM 93 is a state road, so the city needed TxDOT's sign-off to work on it. The Telegram reported that the Temple City Council voted unanimously on March 19 to approve an advance funding agreement with TxDOT. It was required because the work is on a state-owned road and costs more than $1 million. The draft mobility plan says the intersection already met TxDOT's standards for a signal.
TxDOT isn't paying for any of it. The Telegram reported that the city is covering the project with existing certificate of obligation bond funds, and that the state is not contributing money.
Under Budget, and Still Late Getting Started
The work has been in the pipeline for years. The Temple City Council approved a professional services agreement with Waco-based Walker Partners for preliminary design in May 2019. The mobility plan lists the reconstruction from FM 93 to Waters Dairy as funded in FY 2021.
Construction bids came in well under the engineer's estimate. Walker Partners put the probable construction cost of the base project at $13.56 million. On June 16, R.T. Schneider Construction Company submitted the lowest of six bids at $9,711,390.76, while the other bids topped $14 million. The Telegram reported that about $3.35 million of the budget remains beyond the construction allocation and could cover change orders if the contractor and the city agree they're needed.
The schedule took longer. The city originally planned to start construction Aug. 1, and the Telegram reported that the date slipped. Before the November start was announced, city spokesperson Nohely Mackowiak told the paper:
"still working with the contractor to finalize the schedule, but we expect initial work to begin within the next couple of weeks."
The construction contract allows 730 days, or two years, from the city's notice to proceed. Phase 1 is set to take about 10 of those months, which leaves the rest of the contract for the corridor south of Wyndham Hill Parkway.
The Detour Runs Past South Temple Park
The posted detour sends traffic along South 5th Street, which is also where South Temple Park sits. Temple Parks & Recreation lists the park at 5000 S. 5th St. and puts it at 50 acres. Amenities include a playground, shaded swings, a disc golf course, a 0.75-mile trail, restrooms and Lions Junction Family Water Park. The Telegram described the Hartrick Bluff corridor as running through neighborhoods near that park, just west of South 5th.
So for the next several months, families heading to the playground or the disc golf course will share South 5th with drivers who used to cut through on Hartrick Bluff. The city asks drivers in the area to use caution, follow the posted detour signs and allow extra travel time.
The City Is Already Planning the Next Stretch
The growth that explains the 12-inch waterline and the new signal doesn't stop at FM 93. The draft mobility master plan proposes $600,000 for 30% design of a later Hartrick Bluff phase south of FM 93. That design would look at right-of-way needs and could lead to construction if growth speeds up. The plan points to new development in recently annexed areas south of FM 93 as the reason.
That proposal is in a draft plan, and it hasn't been scheduled for construction. It does show how the city sees this road. Temple is treating Hartrick Bluff as a corridor that will keep stretching south, and the closure that started Nov. 2 is the first stretch of it.
If you live along Hartrick Bluff or Wyndham Hill Parkway and want to know how a long construction season and a new signalized intersection could affect what your home is worth, Rachel Holman can walk you through recent sales near the corridor and what buyers are seeing right now. Start with a free home valuation, and we'll take it from there.